Project case study
Iran–Iraq Export Gas Metering Station
EPC delivery of a quantity-and-quality gas metering station at the Naftshahr border point.
ClientIranian Gas Engineering and Development Company / Niroogostar
ConsultantPARS Consulting Engineers
LocationNaftshahr, Iran–Iraq border
ContractEPC
Recorded periodStarted 23 Sep 2013; final handover 10 Apr 2019
Scope of work
Principal project responsibilities
- Engineering and construction of quantity-and-quality measurement systems
- Metering and analyzer procurement and integration
- Central control, ESD and fire-and-gas integration
- Testing, commissioning and final handover
Selected technical data
Documented project information
- Recorded capacity
- 40 million standard m³/day
- Systems
- Metering, analyzer, ESD and F&G
- Application
- Export gas
This case study is rewritten from legacy website records. Current status and time-sensitive details will only be updated after formal confirmation.