EPC contractor and metering systems specialistinfo@skpalayesh.ir
Gas metering skid mounted on its concrete plinth

Project case study

Marjan Petrochemical Gas-Metering System Standardization

Redesign, procurement, installation, testing and commissioning of gas-metering systems to improve compliance and measurement configuration.

ClientMarjan Petrochemical Company
ConsultantMarjan Petrochemical Maintenance Department
LocationAssaluyeh, Iran
ContractRedesign, procurement and construction
Recorded periodAwarded 18 Mar 2024; six-month base term, extended to 22 Sep 2025

Scope of work

Principal project responsibilities

Selected technical data

Documented project information

Main line
12-inch
Fuel-gas line
4-inch
Measurement
Ultrasonic metering with master-meter arrangement